Cut-off wall is a method of installing a rock-fill dam in the ground and can be classified into three types according to materials.
1) Plastic Concrete Wall
It is composed of cement, sand, gravel and bentonite by applying to rock-fill dam of dam or lock.
2) Slurry Trench
Applied to areas not deep in rock-fill dams, it consists of a mixture of existing soil and bentonite.
3) Cement Bentonite Wall
CB Wall is applied to landfill layer, waste layer, etc. and is composed of cement, bentonite and additives to control the curing time.
Leachate Prevention Concept
Select installation method
There are horizontal arrangement systems that control the perimeter of the contaminated area and vertical arrangement systems that control the depth of the contaminated area. When applied to the field, the arrangement system is formed by appropriately combining them.
1) Horizontal arrangement system
According to the groundwater flow direction
➀ Upgradient Placement
➁ Downgradient Placement
➂ Circumferential Placement
2) Vertical arrangement systems
➀ Keyed-In arrangement method Applied to shielding facilities in impermeable layers such as unsanitary landfills such as waste landfills
➁ Hanging arrangement method When controlling lightweight insoluble substances floating in water such as oil, it is applied to shielding facilities in the water permeable layer.